1、GRC構件裝置差錯應契合下列請求;
1. GRC component device error shall comply with the following requirements;
單位裝修面得筆直度差錯≤5mm/層高,且總差錯≤50mm;
Straightness error of unit decoration surface ≤ 5mm / floor height, and total error ≤ 50mm;
單位裝修面的平直度差錯≤5mm/2m,且總差錯≤50mm;
Flatness error of unit decoration surface ≤ 5mm / 2m, and total error ≤ 50mm;
2、 GRC構件裝置前應對建筑物銜接結構外表進行處理,保證其平坦、堅實。
2. Before GRC components are installed, the surface of the building connecting structure shall be treated to ensure that it is flat and solid.
3、 GRC構件外表有缺棱掉角等缺點時,裝置后應選用水泥拌合資料進行修補。
3. If the GRC component has defects such as missing edges and corners on the surface, the cement mixing data shall be selected for repair after the installation.
GRC構件安裝重要步驟
Important steps for GRC component installation
4、裝置接槎應平順,差錯超過5mm時,應進行打磨處理。
4. The joint of the device shall be smooth. When the error exceeds 5mm, it shall be polished.
5、 GRC構件銜接應預留縫隙,并依據規劃請求進行處理。
5. Gaps shall be reserved for the connection of GRC components and handled according to the planning requirements.
6、外架搭設時充分考慮GRC線條的裝置特色及外挑尺度,保證裝置GRC線條時有滿足的距離
6. When erecting the outer frame, fully consider the device characteristics and overhang scale of GRC lines to ensure that the GRC lines of the device have a satisfactory distance
7、裝置前應依據施工圖紙在外墻上彈好標高線、水平、筆直和構件基地操控線以操控GRC構件裝置在同一水平線上。
7. Before installation, the elevation line, level, straightness and component base control line shall be snapped on the outer wall according to the construction drawings to control the GRC component device on the same horizontal line.
8、有防水請求的部位,應進行防水處理,并采納必要的防凍害辦法。裸露于空氣中的鏈接件及焊縫應進行可靠地防腐處理。
8. Waterproof treatment shall be carried out for parts with waterproof requirements, and necessary anti freezing measures shall be adopted. The links and welds exposed in the air shall be subject to reliable anti-corrosion treatment.